The Hume hydro power station holds a licence from the Environmental Protection Authority (EPA) to operate. Under this licence Meridian Energy is required to prepare and comply with a Pollution Incidence Response Management Plan (PIRMP), a copy of which is available here.

Meridian Energy is required to undertake monthly monitoring of two onsite drains. The results of this and other compliance aspects are reported annually to the EPA in the Hume Annual Return. A copy of the most recent Annual Return is available by here.

Environmental Monitoring Results

Sample point one is the main power station drain, which collects all drainage water from within the power station complex. It is discharged into the Murray River. Environmental sampling is required monthly.

Sample Point One

Sample Date
Oil & Grease
Limit = 10 mg/L
January 2018
< 5
February 2018
< 5
March 2018
< 5
April 2018
< 5
May 2018
< 5
June 2018
< 5
July 2018
< 5
August 2018
10
September 2018
< 5
October 2018
6
November 2018
< 5

Sample point two is the switchyard drain, which collects all rainwater from within the switchyard. It flows into a holding tank. This holding tank is required to be sampled prior to it being emptied. If the results are within the licence limits, then it is discharged into the Murray River. If the results are above the licence limits, a tanker truck will empty the tank and take the water away for treatment.

Sample Point Two

Sample Date
Oil & Grease
Limit = 10 mg/L
Total Suspended Solids
Limit = 50 mg/L
January 2018
< 5
< 5
February 2018
< 5
< 5
March 2018
< 5
< 5
April 2018
< 5
< 5
May 2018
< 5
< 5
June 2018
< 5
< 5
July 2018
< 5
< 5
August 2018
< 5
 7
September 2018
< 5
< 5
October 2018
< 5
< 5
November 2018
< 5
< 5